Sorry to jump in, after internal discussion w. the team, we have concerns on revising the metal part comments at this stage, as you may see the sample is already same as 3D aligned and if we are requested to change the metal part at this latest stage, we would need to restart the module making stage again, there will be impacts on:1. AS delivery, we target to send it out by Oct w. revised pointiage as per latest comment, but if we need to change the metal part, we can only submit by mid of wk 422. KPI calculation on OTD which is a very important factor to review our performance, realistic data is always needed for getting the root cause and get improvementSo we would prefer to keep AS shipment on next week w. revised pointiage as requested, hope you can agree.And Eiad will the pic of revised pointiage by today. 