Attached is comment from SG.
I have asked them about material schedule. They told me they hav added WF-04 (Weathered orange bricks) on drawing but as I saw in the drawing they have sent back it doesn't clear and I'm waiting for their answer.
They said now the contrator is on the process of starting construction on site so they would like us to send more information, as we have talked such as section of millwork, floor, wall, ceiling or whatever they need and outstanding drawing as their comment, so the contractor can start their work while we are revising and send them more drawing later.
About payment I have told them and might be takes 3 days or more to proceed this. If I have any update will get back to you.