While rig crew are tripping out the existing ESP completion string, Pump man found water inside tank gain 10 bbl and inform to WOS. WOS inform Jack operator to pull up one full joint for standby and go to recheck the return flow at shale shaker. WOS found a lot of water continue return to shale shaker, so he inform Jack operator to cut the cable of ESP, then Jack operator simulate the well kick horn signal and inform BHI and KIS to cut the cable of ESP. Jack operator report the situation to WOS. WOS inform Jack operator to secure well. Jack operator down tubing and inform technician to down the elevator together, after that they install the low torque valve and close annular by koomey remote on work basket. Jack operator ensure that the well was secured and inform WOS. The situation back to normal condition.