The contractor shall keep the site, including the facilities and adjoining premises, safe and clean at a all time of this contract. The contractor shall remove all materials, wastes, debris and temporary building structure if any, as well as cover the earth surface to leave the site clean ready to use, from the site when the work is finished.
In the case of any incident beyond one's power or any incident caused by the fault or negligence or law avoidance of the owner, which causes the delay of completion, the contractor shall report such activities in written consent to owner for schedule extension within 15 days commencing the date of incident termination.
If the contractor fails to proceed as mentioned in the previous paragraph, the contractor shall abandon the right to request for extension whatsoever, except for the obvious incident caused by the owner.
The extension of contract schedule as mention in the previous paragraph shall be under the owner's discretion to consider own decision.
Contractor shall repair any damages free of charge which occur by contractor within 1 year after job completed. This contract has been made in two identical copies. In witness whereof, the parties hereto have signed this contract in duplicate by their duly authorized representative with the stamp if any as of the date first above written, and each party keeps one copy of the two.