Date 11/24/2559 Summary
1. Aor Bor Tor is doing the extra road surface and drainage (manhole) at front of Grand Himalai. It is expected to be completed within November 2016.
2. I have requested a connecting entrance of the project. Plus requesting drainage of Grand Homalai and Himalai with Aor Bor Tor already.
3. For the trees across the front of the Grand Himalai, they will cut some part of the tree and will finish within December 2016.
4. For Construction Permit of Grand Himalai, they can issue before EIA is done but the number of buildings should not be over according to law before obtaining EIA (meaning we can build only few building) and we need drawing to apply for it.