Step 3: Plan Preparation
Scheduling the project is planned for 4 months. Step by step of kaizen must be followed
to get the actual result of kaizen steps effectiveness. In project schedule, each steps or
activities is perfectly allocated its duration. This project schedule consist 11 activities
which had to finish in 14 weeks of duration time.
Step 4: Organizing Team
The next step in Kaizen will be organizing the Project Team. The team are put together
and expected to come up with a solution to a problem and success in the project
conducted. Target is set due to project planning and project schedule. Specifically,
target of the project is to reduce lead time of sales order processing processes at least
5%