1.1.1 Project overview Houay Por HPP is located in Saravan Province, and it is a run-of-river headrace HPP. Its development task is power generation. The main structures include concrete gate dam of main dam, trapezoidal open channel, concrete core earth-rock dam of saddle dam and open forebay, penstock and ground powerhouse works, tailrace channel, etc. The full supply level (hereinafter referred to as FSL) of the main dam will be El. 322.5m, and the corresponding storage capacity will be 76,000m3. The FSL of the saddle dam will be El. 320.00m, and the corresponding storage capacity will be 135,000 m3. The working discharge for power generation of will be 29.0m3/s, the designed head will be 61.0m, and the total installed capacity will be 15MW.