Dear Khun Surang,
Referred to our asking approval our revised design both interior design and M&E designs as mentioned you, our designer submitted all revised drawing to both department as your leasing team and TS-CWG team since October 2015
For part of revised interior design, we already got your approval documents. For part of revised M&E system design, we have not received the approval document form TS Team yet which our designer submitted to them since 6th October 2015 via our last email below – pls scroll down.
For this case, it is the cause of unable to start construction work following our schedule. Yesterday we had conference call to discuss this issue with Khun Pook and our designer, Khun Pook committed to get it done within today. Hopefully we will receive the approval document on time.
Anyway, we are not appreciated for this slow process from CPN, also please cannot ask us to pay rental fee if we are unable to start our fit-out work following our schedule that we should be started our construction work since 5th Dec.
We are anxious to your slow working team and don't hesitate to receive your kindest support. Look forward to hearing from you very soon.