AGREEMENT:
1. To achieve OE performance targets through improved operational discipline, improving the effectiveness of high priority processes and process safety, being personally accountable for safe choices, and focusing on the environment stewardship and compliance.
1.1 To achieve Zero DAFW case and TRIR 0.22: Agree Action Items;
a. Achieve CHESM audit at job site > 90% for Production related tasks i.e. PVI, MRU catalyst Change out and Chemical Trial program.
b. Support NM report at least 20% higher than year 2014.
c.
d. Share and record OE knowledge to all RMT Tech in shop meeting as weekly.
e. Support RMT team to achieve 90% participation of 24 BBS/year for non-qualified and 12 BAPP/year for qualified observer.
f. Meet standard BAPP Performance for all 6 elements in spider chart are with range 6-12 months and actions implement >90%. Leading and supporting BBS/BAAP program by targeting every RMT personnel to carry out one observation weekly and reinforce to complete individual target every month.
g. Share safety moment during shop meeting and OE meeting.
h. Achieve 3 observation/rotation on WHP(P/F visit, MSW audit, V&V, )/1/week)
i. Support 100% PTW Audit for open flame and CSE, 50% for other permits on WHP.
j. Support discipline for on time report, investigation and action close out - > 90% compliance.
M. Attend PSM awareness through training, promotions & campaign and strengthen culture of incident reporting.
n. Tracking and follow up WHP clean up to complete as 2015 kpi = 18 Platforms/year.