Here the issues I currently have for these increases:
1.- PCB from Chinpoon (ME PN: 9031013), according with my system I need it here in my plant by 11/28, currently shipping date from Chinpoon is around 12/12 (due to LT)…… $1200 USD is the fee in order to expedite Chinpoon´s production process in order to ship on time to meet my requirement,.
Please confirm if you approve this.
2.- LED (ME PN1: 9020102) MPN: L-433GDT , Purchasing Dept has just found some pieces in bulk presentation (instead of tape and reel)…. I am not sure if we can use it., I will check with manufacturing.
3.- Conector, Header (ME PN: 9041095) MPN: TYCO 1376515-1. LT 17 weeks, they will have material available until Jan 2017…. According with my system I need material by 11/28, so the expedite fee from TYCO is
$250 USD to improve the shipping date….. (they are still checking when will be)
Please confirm if you approve this.
I only have 500pcs in WIP + around 200pcs more available to build and NO more due to these shortages.
Please let me know how to proceed.
Will keep you posted.