Dear All Concern
Sorry for send by BCC.
Regarding annoucement meeting on last week.
For SRG's parts , We has already start tooling making with all of you.
Thus I would like to issue our document to all of you.
Please fill up document below and send back to DENSO on 10 Nov.
I will advance check before invite you to check your schedule together.
1.Production Preparetion Schedule
2.Schedule for tooling making
3.VA-VE Format
For 1st D-SPTT activity , We will separate supplier for 3 groups.
1st Group , I would like to invite you to explain about part design and master schedule at DIAT.
2nd Group , I would like to invite you to explain about master schedule at SRG.
3rd Group , I would like you to only issue master schedule to me.
For group of supplier , I will inform and will set up appointment to check document to all of you later
Thank you very much