Further, AWTC has enchased advance payment guarantee of amounting SAR 49.8 million, as per settlement and services agreement, dated 31 March 2016, with Abengoa and hence incurred no loss on the settlement arrangement. The estimated cost to complete the project is calculated on basis of above arrangements. The cost to complete the project by under new arrangement is SAR 534 million while the cost to complete under arrangements with Abengoa is SAR 539 million.