Dear K. Pansak
With reference to the meeting with the operation committee that give me the timeline for necessary planning with gondola company, please find gondola installation planning below.
Although, I hope the pool will still be in use when you have the party next Saturday but given the procedures we have to go through draining the water and to start working on Monday 19th, I have no choice but to follow the schedule given by the gondola company below.
DATE DESCRIPTION AUTOQUIP (GONDOLA COMPANY) QUICK PAINT THE PARK
13.1.15 TU INSTALLING GONDOLA CHIDLOM BUILDING SAFETY MONITOR
14.1.15 WE INSTALLING GONDOLA CHIDLOM BUILDING SAFETY MONITOR DRAIN OUT WATER
15.1.15 TH INSTALLING GONDOLA SOMKID BUILDING SAFETY MONITOR
16.1.15 FR GONDOLA INSTALLATION COMPLETION SOMKID BUILDING SAFETY MONITOR
17.1.15 SA GONDOLA CHECK BY ENGINEERS
18.1.15 SU GONDOLA CHECK BY ENGINEERS SAFETY AND PROTECTION
19.1.15 MO START WORKING MORNING CHECK + ONSITE TECHICIAN START WORKING
Thank you very much,