OK so found a new practice which the user population manages to challenge us on a daily basis. Item 4 in the email below is most interesting1. Requisition is created from a work order 203121512. Work Order has 3 operations3. Work order is scheduled4. All materials are ordered against operation 30 which has a delivery date in Feb 2016 which is what prints on all the POs and will also be used in reservations…… the materials are actually required this Friday….. not sure if any of the following processes are implemented in Thailand to advise the suppliers of the real datesa. Smoke signals….. probably not as fire on Refineries is not a good thingb. Carrier pigeons…….. again normally considered vermin and won’t last longc. Email…….. ummm good second process decreases efficiency nicely….Please could you take a look and see if this is systemic as it must cause holy hell as far as recycle….