D-3 Evening: Stage setup related meeting
TH-Reply (0522): Please specify meeting timeline so we can allocate in local production set up schedule
As of now, please schedule the meeting for 19:00 on D-3. Exact time will have to be confirmed later when we book
our flights.
 D-1 Evening: Load-out related meeting
TH-Reply (0522): Noted / ***Please let us know meeting timeline.
Specific time will be discussed on-site by Stage Manager
  Main Curtain Truss & Projection Mapping Truss: extend 2M on SR side
 (position shift for wire to motor drop down point)
 TH-Reply (0522): Noted for Main Curtain Truss & Projection Mapping Truss’s extension.
LX#5 should also be extended 2M on SR side
  Shift position of Projection Mapping Truss: between LX4 & LX5
 TH-Reply (0522): Noted about Projection Mapping Truss’s new position.
 ***However, could you please specify ideal gap between each trusses back to us, so that we can manage local
 hanging position to match up with venue’s rigging condition.
We do not advise on ideal gap between trusses because depending on the local stage floor deck size, the location of
trusses may change for each venue.
Do note the following notes from the checklist –
LX5 should be at the downstage edge of cube lift
LX6 should be above the cube lift area
LX7 should be at the upstage edge of cube lift
Now with the above three trusses in place, all other trusses located downstage from LX5 should be rigged almost at a
consistent distance from each other. (LX1 ~ LX4, main curtain truss and projection mapping truss)