Furthermore, the option 2 that has been provided the over working time for the resource.
This option resolves the problem by using the Change Working Time.
This would be a problem if the case study indicates the overtime working cost.
Therefore, the overtime working cost has been assume by using the same rate with normal days (Monday to Friday) ($900 per day for Principal Architect, and $500 per day for Draftsperson).
As a consequence, the cost of project that has been resolved by changing the time is the same as other options.
the extra time using so as to work expense has been accept the same rate with typical days (Monday to Friday) ($900 every day for Essential Draftsman, and $500 every day for Draftsperson). As an outcome, the expense of venture that has been determined by changing the time is the same as different alternatives. This arrangement is isolated into 2 alternatives as can be found in the Table 3.2.