PhasingPhasing of the school with phase 1 as the Library. In order to facilitate ODEDIM and SATIMO in finding the necessary funding, the construction of the school for deaf children was divided in 3 phases. Phase 1, the pilot project, concerns the building of a library and two adjacent public squares, one bordering the street and one oriented towards the future school. Phase 2 is currently under construction, and consists of two classrooms, a small sanitary block and a playground. Phase 3 will result in four classrooms, a big sanitary block, and a refectory with kitchen. Phase 4 is a student-run workshop and extra classrooms.