5.4.2 The Owner shall prepare and deliver to AHR the monthly construction progress reports, in reasonable detail, outlining the progress of all major activities related to the design, construction, renovation and fitting out of the Project. Each such monthly report shall be delivered to AHR by not later than the 10th day of the month following the month to which such report relates and shall include a summary of major construction activities completed in the previous month, labor union disputes or problems (if any), the status of significant tests and inspections, variations from accepted designs, deviations from the current project schedule, and major activities expected to be accomplished during the upcoming month.5.4.3 AHR shall revert within 5 (five) Business Days upon receipt of the above mentioned reports with any comments or suggested modifications.