There is much work to do between now and the 16th.
Please meet in my office at 09:30 this Monday to do full review, including:
have pre-qualified suppliers for all main cost items, and have those local suppliers entered on our AVL;
have components for Orders 1069987 & 1077648 (SIHI Malay) in-house at Incoming Inspection;
have QPs & WIs approved and have a training plan approved (identifying trainers & trainees);
have an organisational structure/flowchart for the project approved (with responsibilities clearly defined).
I hope we can do all possible to complete these tasks by Friday 13th. If there is anything preventing this from happening, please let me know on Monday morning so that we can together set corrective actions.
Dear Florian & Achim,
Thank you for your support on this important project.
I have looked through the outstanding actions and would like to arrange a call with you so that we can be better prepared for your visit. In addition to the above, I can add that I have initiated another search for Titanium shaft material, but please let me know the feasibility of substituting SS316L. Please let me know when we can talk, or drop me a message so that I can take further action.
I am here to provide you with all the support and feedback you need to make this transition on-time and successful.