Dear khun Natthapoom ,
Please see in sheet Plan offline Jun – Sep 14 , ( detail is plan offline & forecast )
I already plan assembly in Jul for # 2-4 ,
And actually there are production on Kick Off event on July 22nd.,
Anyway , the thing you have to worry is your process to support CKD arrive to TCMA at least 12 units/ months
In order to support your production plan.
Please note :
1.CKD # 3-4 will arrive TCMA approximately on 23-25 June 14.
2.Please sign acknowledge in Plan offline Jun – Sep 14 , and send back to me.