PLC plan to trial SAJ Japan shipping as schedule below .
Loading testy will start on 10:10 am at ESC factory)
1.Truss Packing ==( Plan to finish packing on May 4).
2.Truss stacking (Top stacking center truss)
3.loading test into container,lashing.
3.Transportation test (AMEC<-->Bang-na)
4.Un-loading test (on platform)
5.Quality check after un-load.
Then, would like MELT arrange F/L,manpower and equipment for loading and un-laod too.
Note: Already booking container for this trial (40HC=1
Thank you &Best Regards,