Refer to our current schedule, we target to issue out Hardscape details at the end of this month.
But there are many hardscape detail works to be completed and we need sometime to finish. We would like to ask your advice for the best coordination. We understand that the construction will be soon started , so we think to send out the hardscape details one by one, which will be according to the floor and zoning.
For example, we will send out the Master Plan Series of 1st, 6th, 7th and 9th floors at the end of this month and the next target will send out 2nd floor zone B, C, D at mid of May and the rest will issue out by the end of May.