Hi K Pitukpong
could you please provide a list - loft X loft of the units that your team along with Savills have carried out their standard QA / QC inspections on, where any identified incomplete work or defects have been rectified and that are now 100% complete, I do stress complete and defect free ready for the owner’s final inspection and signoff ?
note:
• all understand that when the final owner inspection is carried out there may be a few additional defects identified
• the owner inspection is a part of the handover / completion process not the beginning of QP’s QC process
I suggest that standard industry processes are followed so that QP can complete and close the project soonest.
Once this documnet is inhand and if the work is to the level of completion that has been agreed I am sure that the payment can be quickly made.
When can the list thatdocument has been previously requested on a number of occasions be provided ?
Thanks and regards,