he data ROM is followed everyday. For the case pattern 2, we will cooperate with MAR for schedule shipment. If S/W still not finish in Melina, we will arrange only standard program for shipment first. Then we have to send the special S/W for replace at site by request reconstruction way.
For the case of special S/W with pattern 1. This case we have to modify by our self. At this moment, we still have only one engineer who able to do it. Our S/W engineers were resign. Now we are under training to new engineer for the special S/W. Also on Oct'14 Melina engineer will come to support us at Amec.
By the way, we ELE department always monitor the status of control panel shipment. We confirmed the control panel is able to assembly as normal without S/W.
Please kindly consider and comment.