b) Get base release for equipment document. Actual equipment base & foundation or steel structure shall be checked to ensure compatibility prior starting work.
c) Before either equipment or cranes arrive on site, the following activities shall be carried out
i. Remove anchor nuts from anchor bolts, store bolts and clean anchor threads.
ii. Mark exact axes on foundation
iii. Padding shall be cured min.3 days or have shimming ready if equipment is mounted within a steel structure.
iv. Where vessels are installed within steel structures, certain element shall be left-out and installed during equipment installation.
v. For Horizontal Vessel and Heat Exchange, sliding end fixed end plates shall be installed if applicable.