Regarding this re-layout for ELC Section, I have some suggest to reconsider.
1) Production delay on Apr11'14 shall be --> Zero.
2) The re-layout work schedule shall be more shorter than this, shall be finished all layout and Facility ready to production on Apr16'14
the Apr17-20'14 shall be buffer. May we have to increase manpower, or sub-contractor if necessary.
3) Item concern safety shall be included to confirm---> before start to production.
This plan is high possibility to effect the production start on Apr21'14
In the passed there are many case of re-layout work incompleted when we started the production, effected delay.
Shall be reconsider, thank you for your co-operation.