Technical Terms:
D-3 = Set Up Day 1 / Load in
D-2 = Set Up Day 2
D-1 = Set Up Day 3 / Technical Rehearsal / Artist Rehearsal
D-0 = Show Day + Load Out
 .................................................................................................................................
- Refer to Tour Production’s info;
 D-3 Evening: Stage setup related meeting
TH-Reply (0522): Please specify meeting timeline so we can allocate in local production set up schedule
As of now, please schedule the meeting for 19:00 on D-3. Exact time will have to be confirmed later when we book
our flights.
 D-1 Evening: Load-out related meeting
TH-Reply (0522): Noted / ***Please let us know meeting timeline.
Specific time will be discussed on-site by Stage Manager
  Main Curtain Truss & Projection Mapping Truss: extend 2M on SR side
 (position shift for wire to motor drop down point)
 TH-Reply (0522): Noted for Main Curtain Truss & Projection Mapping Truss’s extension.
LX#5 should also be extended 2M on SR side
  Shift position of Projection Mapping Truss: between LX4 & LX5
 TH-Reply (0522): Noted about Projection Mapping Truss’s new position.
 ***However, could you please specify ideal gap between each trusses back to us, so that we can manage local
 hanging position to match up with venue’s rigging condition.
We do not advise on ideal gap between trusses because depending on the local stage floor deck size, the location of
trusses may change for each venue.
Do note the following notes from the checklist –
LX5 should be at the downstage edge of cube lift
LX6 should be above the cube lift area
LX7 should be at the upstage edge of cube lift
Now with the above three trusses in place, all other trusses located downstage from LX5 should be rigged almost at a
consistent distance from each other. (LX1 ~ LX4, main curtain truss and projection mapping truss)
  Cut 900 depth of Main stage 1st level
 TH-Reply (0522): Please consider local stage size as below;
 Main Stage Zone
- Main Stage Zone : 15.86 x 34.16 + 1.80 Meter (D x W + H)
- Main Stage 1st Level: 7.32 x 24.40 + 1.80 Meter (D x W + H)
- Main Stage 2nd Level: 7.32 x 24.40 + 2.44 Meter (D x W + H)
Please send me the CAD drawing.
We would like to raise the Mainstage 1st level to 2.1 meter height (instead of 1.8).
Mainstage 2nd Level height should be 2.47 not 2.44 (our cube lifts are exactly 2.47 in height)
 Question:
- With local main stage size above, is it necessary to cut 900 depth of 1
st stage level as your request?
I need to see the stage plan first before I answer this question
- Height of Main Stage 2nd Level is calculated from Ground Floor Level, is that correct? YES