Regarding to paper tube for SWS-T,
Below E-mail on May26 to Nat.
This is my instruction how to arrange paper tube.
1. UOI requests to keep min order
Long : 1,200 pcs/order
Short: 200 pcs/order
2. UOI can accept partial delivery for Long size
400pcs/delivery
3. UOI can accept different day delivery.
For STEC side, they can accept above 4 points and arrange PO and forecast as
follows.
1) STEC keeps min order.
2) STEC shows partial delivery plan when they arrange PO
3) STEC can give 3 month forecast.
4) STEC needs to give 3 month notice when they change size or stop
order.
*Important (Oct 13)
UOI needs to arrange following forecast.
If their order is only 200pcs, we have to request forecast to SWS-T to
check future qty.
And then UOI will order to supplier first and keep stock here.
SWS-T and STEC will have responsibility to clear stock.
Your next job should be,
1) UOI requests forecast to SWS-T.
2) Check qty.
3) UOI will order first to supplier.
4) UOI will deliver 200pcs to STEC.
5) SWS-T will have a responsibility to clear stock following forecast.