The planning was updated following master plan which the latest version was on the audit dated. The overall progresses were
28.45% which delay 1.97% compared to the master plan.The report was provided by weekly and monthly to consultant, for following
of progress was showed for delay cause such as MOM no.MOM-C-1401.02-0020-0033 on 20/01/2016,obstruct for other subcontractor,
the result were satisfied.